Final checks being done on Northwest Transmission Line (Terrace Standard)

INSPECTION teams are now going from tower to tower along the 344 kilometre length of BC Hydro's Northwest Transmission Line, methodically checking each one prior to the line being energized sometime next month.

The checks are part of the commissioning of the $736 million 287 kilovolt line, construction of which was officially completed June 7, says Jim Shepherd, the BC Hydro manager in charge of the project.

(To read complete source article, click "Terrace Standard")